1995 March - August
Thompson Minwax spun off from Eastman Kodak in 1994 to investment company Forstmann Little needed to quickly implement an ERP system to support its two plants and multiple distribution centers. Working with Deloitte & Touche the company selected JBA System 21 as the ERP system with the caveat that it need to be implemented by June 30th 1995 so that the existing ERP running on Eastman Kodak systems could be retired by end of August. The contract was signed at the end of March and I was tasked with putting a team together to complete the phase 1 implementation of the finance, order processing, inventory management, and supply chain modules. Phase 2 would follow and would include manufacturing systems at the plants.
As the analysis began the team soon came to realize that significant modifications would be required to ensure a successful implementation. A number of the business analysts on the team had limited experience and one of the classic specifications had a series of screen shots along with the immortal words "a workfile may be required"and not much else to define a re-write of order entry.
The project plan I put together required significant overlap of the activities to meet the extremely tight deadlines and so we set up a conference room at JBA as the war room and bought key customer leads to the war room to be close to the developers in these initial releases. Then as we began to make progress we set up corresponding war room at the customer site so that the developers and analysts could work hand in hand developing and testing the modifications close to the customer. In parallel on site at Thompson Minwax the user team continued to work through the standard application training and working on data conversion and report design.
As spring moved to summer the system testing, user testing, training and data conversion went into full swing. The team migrated back and forth along almost the full length of NJ on a weekly basis.Managing change requests became a crucial part of the project management ensuring that only critical issues were addressed in the initial product release.
July 4th came the intensity of the project reached breaking point literally with continued issues with the user acceptance testing and continual air conditioning drop outs making the working conditions almost unbearable. The first of the go live dates was postponed. The team stepped up the pace to make sure the user training was completed on time, interfaces developed and tested and final UAT was completed. Acting as solution architect, user testing lead and project manager took me to new levels in my experience on projects and made me focus on the processes of improving project delivery under very tight time lines.
At the start of August the project went live with a number of issues still outstanding but nothing that would interrupt the business flow. The team stayed on board through August and September to see the production facilities implemented. At the end of September the project was handed over to another project team to complete the installation and follow up with additional change and modifications that had been prioritized after go live.



Project List


